- For proper surface profile, all hot dip galvanized parts are Brush-Off Sandblasted to SSPC-SP-7, commonly referred to as “sweep blasting”.
- 130 F degreaser in high-pressure spray for approximately 60 seconds.
- Fresh water rinse in high-pressure spray for 30-60 seconds.
- 130 F Iron Phosphate in high-pressure spray for 60-90 seconds.
- Fresh water rinse in high-pressure spray for 30-60 seconds.
- Seal rinse in high-pressure spray for 30-60 seconds.
- De-Ionized water rinse for approximately 60 seconds
- Dry-off. 10 minutes at 250 F for 10 minutes.
- Application of Rohm & Haas’s Zinc Rich Epoxy Primer P/N 13-7004 applied permanufacturers recommended application. Gel only (not full cure)
- Polyester Powder topcoat application per manufacturer’s recommended application method.
- Normal cure is 375 F (part temperature) for 12-15 minutes
- All jobs Impact Tested to ASTM D2794 and Adhesion Tested to ASTM D3359.